Fiscal Year End
Fiscal Year End
Introduction to FYE
Schedule
June 14, 2024: New Vendor & Vendor Reactivation Requests
June 20, 2024: Special Assignment Payments & Student Special Project Contracts
All full time Special Assignment Payments and Student Special Project Contracts (formally known as Salary Vouchers) must be submitted by June 20th in order to be paid within FY24.
Any Full Time & Part Time or employee labor redistribution for FY24 (for BW Pay#14) must be initiated by department no later than July 8th.
Any student labor redistribution for FY24 (for BW Pay#14) must be initiated by department no later than July 16th.
June 20, 2024: Requisitions & Change Order Requests
Last day to process requisitions or change orders * for FY24 goods and services. Please place your requisition (for active vendors only) with appropriate documentation and required approvals to allow conversion to purchase order. Goods and/or services physically received by the close of the fiscal period will be charged to the FY24 budget. See note two below for exceptions.
*Change Order requests to reduce po amounts or adjust for payment of items received before June 30, 2024 will be processed.
June 20, 2024: Systematic Batch PO Closing
June 20, 2024: Amazon
June 27, 2024: ODP (Office Depot) Orders
June 27, 2024: Departmental Deposits
June 28, 2024: Open POs
June 28, 2024: Receiving
Goods to be charged against FY24 budget must be physically and electronically received in Banner by the close of business.
*Important: Banner receiving should only be completed after services are performed and/or goods have been delivered. This applies to all purchases in Banner, regardless of the funding source, including internal and external grants.
June 30, 2024: BoA P-Card Purchases
June 30, 2024: Travel
July 05, 2024: Non-PO Payment Request
July 05, 2024: AP Doc Cutoff
Cutoff date for processing Non-PO payment request, student & non-employee travel expense reports, and invoices against purchase orders to be recorded in fiscal year 2024. See note 3 below regarding memberships & subscriptions.
*Ensure sufficient time for travel encumbrances to be fully approved and expense reports to be submitted by July 5th*July 08, 2024: Labor Redistribution Requests: Employees
July 10, 2024: BoA P-Card Allocation
July 12, 2024: Journal Entry / DCA
July 16, 2024: Labor Redistribution Requests: Students
Important Notes & Reminders
1. |
Entering a requisition in Banner by the cutoff date (6/21/24) does not guarantee that the expense will be processed and paid within the current fiscal year (FY24). Due to ongoing supply chain disruptions, orders may not be processed and fulfilled during the current fiscal year (FY24). Continue to anticipate shipping delays, out of stock items and back orders. Please plan accordingly and do not wait until the cutoff date (6/21/24) to submit a requisition. |
2. |
Cutoff date exceptions for requisitions:
Amazon activity from June 21st to June 30th may be processed via requisition. All other cutoff dates (DCAs, Office Depot, etc.) apply to the funds noted above. |
3. |
All invoices should be forwarded to the Accounts Payable department or sent to invoices@rowan.edu Note: Memberships/Subscriptions spanning two fiscal years: FY24-FY25 or purely for FY25 must be processed and paid by June 28th in order to be reflected in FY24. |
4. |
Travel FY24 manual encumbrances do not roll over into FY25 — this cannot be changed due to Banner systematically closing out the encumbrances for the fiscal year-end roll
|
5. |
FY24 Operational Budget surplus will not carry forward into FY25. |
6. |
FY25 Non-operating funds budgets (special programs, etc.) will not be set up in Banner until Finance completes year end system roll procedures, tentatively set for mid-July 2024. |
7. |
POs open at the completion of FY24 will carry forward to FY25 and charged to the fiscal FY25 budget.
|
8. |
Journal entry feeds include: telephone, stationary, utility allocations, postage, custodial back-charges, labor & material back-charges, duplicating, catering, copier, fuel charges, atrium card and BOA Pcard correction activity. |
9. |
Cutoff date exceptions for DCA’s:
Grants with Cost Sharing – submit fully completed DCAs by noon – July 26th |
10. |
Additional Procurement information can be found here. |
Contact Information
If there are any additional questions or concerns regarding the year end closing process, please contact:
Accounting Issues: |
Kyle Beach |
beach46@rowan.edu ext.53714 |
Accounts Payable Issues: |
Stacey Bucci |
buccis@rowan.edu ext.64117 |
Budget Issues: |
Eric Williams |
williamsej@rowan.edu ext.64337 |
Bursar Issues: |
Adrienne Graber |
grabera@rowan.edu ext.65162 |
Procurement Issues: |
Chris Haley |
haley@rowan.edu ext.64149 |
Grant Issues: |
Lisa Ciliberto |
ciliberto@rowan.edu ext.65534 |